Consultation on a review of the Feed-in Tariff scheme

Published On: September 3rd, 2015Categories: News

Last Thursday (27th August) DECC launched their much anticipated consultation on reviewing the Feed-in Tarrif (FiT) – and what a bombshell it was.

The conservative party had clearly targeted renewables as part of their manifesto and on one hand they have to be commended for delivering on their pledges.  On the other, these proposals stand to decimate an entire industry, cause the loss of 1000’s of green sector jobs and halt the deployment of sustainable onshore renewable energy generation across the UK.

Whilst the sector had been expecting a significant ‘squeeze’ to the commercial parameters promoted through the FiT, the current proposals are set to make most projects economically unviable after the changes come into force as proposed in January 2016.  There is also fear that many manufacturers will be forced out of business, bringing into question future warranties, servicing and maintenance of existing products.  This will have a big impact at the small to medium scale installations where adoption has been by individuals and small businesses.

The consultation proposes a banding review as follows:

Proposed Generation Tariffs for Jan 2016 (p/kWh, Nominal prices) Ofgem Tariffs for installations with an eligibility date on or after 1 October 2015 (p/kWh, 2015/16 values)
Solar PV
0 -10kW 1.63 <4kW 12.47
4-50kW 11.30
10 – 50kW 3.69
50 – 250kW 2.64 50-150kW 9.63
150-250kW 9.21
250-1000kW 2.28 250-5000kW 5.94
> 1000kW 1.03
Stand alone 1.03 Stand alone 4.28
Wind
<50kW 8.61 0-100kW 13.73
50–1500kW  4.52 
100–500kW 10.85
500–1,500kW 5.89
>1500kW 0.00 >1500kW 2.49
Hydro
<100kW 10.66 <15kW 15.45
15-100kW 14.43
100-500 kW 9.78 100-500kW 11.40
500-2000kW 6.56 500-2000kW 8.91
>2000kW 2.18 >2000kW

 

It has to be stressed that these figures are only for consultation at the moment, but there are very few expectations of a huge shift in stance given the wider stance promoted by the government so far.

There is currently a big push to make projects safe for the ROC grace period or to get them installed before March 2016 (ROC) or January 2016 (FiT) next year.  Wilson Fearnall can provide support in all areas of renewable development and are able to provide support during this important period.

Beyond Christmas? We will have to wait and see if any phoenix will rise from the ashes.  Lets hope it can.

 

 

 

Related posts

  • Published On: February 26th, 2019

    Robots, vertical farms and virtual fencing could soon be part of the British farming landscape, according to a trailblazing report to be launched at the NFU Conference on 19th February. The Future

  • Published On: February 26th, 2019

    Transport for the North - a partnership consisting of 20 local transport authorities and business leaders, together with Network Rail, Highways England, HS2 Ltd, and Central Government – have

  • Published On: February 26th, 2019

    The new Electronic Communications Code has been causing much trepidation in the Telecoms world, with operators and site providers at loggerheads over its interpretation and how this will affect

  • Published On: December 4th, 2018

    HS2 have launched a consultation on their draft Environmental Statement and draft Equality Impact Assessment for the Phase 2B route between Crewe and Manchester and the West Midlands and

  • Published On: December 4th, 2018

    The Government’s long-awaited Agriculture Bill is progressing through parliament with a third reading due in December. The Bill will set the framework for the biggest reform to the farming

  • Published On: December 4th, 2018

    A few of the main points to take from Octobers budget: • Annual Investment Allowance to rise from £200,000 to £1m for all qualifying investment in plant and machinery