Is battery storage the answer ?
In the energy industry a lot is being said about the development in battery storage technology. After the fall in renewable incentives a lot of focus is being given to co-locating battery storage alongside existing generating plant, particularly wind and solar.
While the theory is sound, co-location is not the simple proposition it first seems. On top of technology choice, developers and operators need to consider the following:
- Land Rights – new rights are likely to be required for siting any ancillary equipment alongside existing plant.
- Planning Permission – in the majority of cases a new permission will be required. If a Local Planning Authority can be persuaded to allow something under an existing consent make sure this does not impact on existing contracts and support payments.
- Grid connection – how and where an export connection is metered will have contractual and cost implications to the new and existing installations.
- Support – if a battery reduces the level of support for the existing generator under FiTs or ROCS any potential commercial gain can be drastically overshadowed.
- Offtake – existing PPA agreements will need to be reviewed to account for the change in nature of the supply.
- Finance – consent from any third party lender will likely be required for any changes to the current situation.
- Insurance – will existing insurance policies cover the addition of a battery? Certainly, a declaration of any changes needs to be made.
All of the above can be overcome with careful consideration, but finding the balance can be difficult. In our view the wider contractual complexities are as limiting as clear guidance on technology and batteries are not yet the practical panacea some might suggest. Specialist support should be considered in many areas if considering such a project.
Related posts
February saw the opening of the window for this years Countryside Stewardship (CS) applications and we are urging farmers and landowners to undertake an early review of their options
Landowners who have sites with development potential should be promoting and preparing planning strategies now so that they are ready to move quickly as planning opportunities arise at a
This probably isn't news to anyone in the industry, but development and investment appetite for new large scale solar sites is as strong as ever. With all political leaders
MHCLG has published a consultation document seeking views on possible amendments to permitted development rights to support deployment of the 5G telecommunications network. Alongside extended powers granted to operators under the updated Electronic
Despite pledging the development of HS3, Boris is nervous about the costs and delays of HS2. This review will certainly not make things happen faster or save any money -
The revised National Planning Policy Framework was updated on 19th February 2019 and sets out the Government’s amended planning policies for England and how these are expected to be applied.