Is battery storage the answer ?
In the energy industry a lot is being said about the development in battery storage technology. After the fall in renewable incentives a lot of focus is being given to co-locating battery storage alongside existing generating plant, particularly wind and solar.
While the theory is sound, co-location is not the simple proposition it first seems. On top of technology choice, developers and operators need to consider the following:
- Land Rights – new rights are likely to be required for siting any ancillary equipment alongside existing plant.
- Planning Permission – in the majority of cases a new permission will be required. If a Local Planning Authority can be persuaded to allow something under an existing consent make sure this does not impact on existing contracts and support payments.
- Grid connection – how and where an export connection is metered will have contractual and cost implications to the new and existing installations.
- Support – if a battery reduces the level of support for the existing generator under FiTs or ROCS any potential commercial gain can be drastically overshadowed.
- Offtake – existing PPA agreements will need to be reviewed to account for the change in nature of the supply.
- Finance – consent from any third party lender will likely be required for any changes to the current situation.
- Insurance – will existing insurance policies cover the addition of a battery? Certainly, a declaration of any changes needs to be made.
All of the above can be overcome with careful consideration, but finding the balance can be difficult. In our view the wider contractual complexities are as limiting as clear guidance on technology and batteries are not yet the practical panacea some might suggest. Specialist support should be considered in many areas if considering such a project.
Related posts
Secretary of State for Transport Chris Grayling is expected to confirm the new route for Phase 2b of HS2 later today. This announcement coincides with the award of approx
The Valuation Office Agency (VOA) has announced changes to business rates for solar PV systems and these new rates are set to come in to force in April 2017.
One of the intentions of the Planning Act 2008 was to make the permitting of major infrastructure projects more straightforward by combing planning consent and the Compulsory Purchase Order (CPO)
The current local electricity distribution network has been supplying North Shropshire with electricity reliably for many years. But with future growth plans in the region planned up to
The economic viability of commercial rooftop solar installations could be severely damaged next year under plans to increase business rates taxes by up to eight times the current levels following
As at the start of February 2016, many farmers will not have received their 2015 BPS payments. The RPA is under increasing pressure to make these payments and we