Government publishes response to Water NSIP Consultation
Earlier today DEFRA published their response to the Consultation on National Policy Statement for Water Resources Infrastructure – types and sizes of projects. This effectively sets the criteria to determine a proposals classifiacation as a Nationally Significant Infrastructure Project.
The key intended changes to the thresholds in the Planning Act 2008 are stated as:
Reservoirs
- increase in volume held back to 30 million m3 (30,000 megalitres) with a qualifying figure of 80 megalitres per day deployable output.
Transfers
- reduction in the threshold from the current 100 million m3 to developments which are expected to exceed 80 million litres per day deployable output.
Desalination
- introduction of a specific definition for desalination plants which exceed 80 million litres per day deployable output.
Effluent reuse
- no separate definition envisaged, but schemes that are considered to be nationally significant, could be directed into the NSIP regime.
Related posts
The UK Government has published Contract for Difference strike prices for renewable technologies under Electricity Market Reform and a summary of key contract terms. Strike prices In summary, the
The Co-op Bank is preparing to spin off its renewable energy lending operations into a new business that could lead to the stock market listing of a portfolio
In their continuing programme for wholesale change of the Town Planning system the Government have now published a consultation document on further changes to Permitted Development Rights. The proposals