The current local electricity distribution network has been supplying North Shropshire with electricity reliably for many years. But with future growth plans in the region planned up to 2026 and beyond, Scottish Power Energy Networks (SPEN) need to reinforce the network and provide additional capacity.

SPEN are currently consulting on a new 132kV overhead line between substations at Oswestry and Wem.  The consultation runs to 9th September and anyone wishing to make representations can do so here.

Whilst the current proposals are for a single circuit 132kV line mounted largely on 12m high trident wood poles, the project still falls under the Planning Act 2008 as ‘Major Infrastructure’.  As such a specific consenting process needs to be followed that will also grant SPEN powers to acquire the rights they need to construct and operate the project.   Updates will be posted to the PINS website.

If you are an affected landowner you should have already been contacted as part of the land referencing process.  Should you need support or advice about any of the next steps or the duty of SPEN to compensate please get in touch.

Related posts

  • Published On: February 26th, 2019

    Robots, vertical farms and virtual fencing could soon be part of the British farming landscape, according to a trailblazing report to be launched at the NFU Conference on 19th February. The Future

  • Published On: February 26th, 2019

    Transport for the North - a partnership consisting of 20 local transport authorities and business leaders, together with Network Rail, Highways England, HS2 Ltd, and Central Government – have

  • Published On: February 26th, 2019

    The new Electronic Communications Code has been causing much trepidation in the Telecoms world, with operators and site providers at loggerheads over its interpretation and how this will affect

  • Published On: December 4th, 2018

    HS2 have launched a consultation on their draft Environmental Statement and draft Equality Impact Assessment for the Phase 2B route between Crewe and Manchester and the West Midlands and

  • Published On: December 4th, 2018

    The Government’s long-awaited Agriculture Bill is progressing through parliament with a third reading due in December. The Bill will set the framework for the biggest reform to the farming

  • Published On: December 4th, 2018

    A few of the main points to take from Octobers budget: • Annual Investment Allowance to rise from £200,000 to £1m for all qualifying investment in plant and machinery