Major Infrastructure and Compulsory Purchase

Published On: July 29th, 2016Categories: News

One of the intentions of the Planning Act 2008 was to make the permitting of major infrastructure projects more straightforward by combing planning consent and the Compulsory Purchase Order (CPO)  into the Development Consent Order (DCO).  It is debatable whether or not it has had the desired effect, rather than merely front loading the process to the statutory pre application stages which lie outside of the determination period set for PINS.

Application-process-diagram2

The governments own illustration above sets out the timelines involved in the DCO process, but it doesn’t show that the pre-application process is often between 3 and 5 years.

Either way, on approval the developer will have gained powers to obtain the specific land and rights that are required to carry out the development over land in which they have no existing legal interest.  These developers are not only the large energy companies, authorities and agencies operating in the public good as one might expect, but include numerous private enterprises operating on a purely commercial basis.

We are starting to see more projects coming through the process from those that are high profile, such as HS2, to more local developments such as Wrexham Energy Centre and SPEN’s new 132kV line.

The developer is strongly encouraged by PINS to seek voluntary agreement to acquire land rights early in the DCO process, ideally before the application stage, but for affected landowners the threat of compulsory powers can often confuse their negotiating capacity.

Recent changes to the compulsory purchase rules have been brought in by Part 7 of the Housing and Planning Act 2016 and the government is consulting on further reforms, all of which makes the process more complicated than ever before.

Any landowners who are approached as being affected by a major infrastructure project should take expert advice before considering their next steps.  There is often no need to be pushed into a hasty decision given the timeframes over which these projects gestate.

 

Related posts

  • Published On: November 26th, 2025

    The Peak Cluster carbon capture and storage (CCS) project is a major new infrastructure scheme planned for the Midlands and Peak District. Its goal is to collect carbon dioxide

  • Published On: November 26th, 2025

    Resolving Compulsory Purchase Claims Early: Why early conversations, mediation and independent advice lead to better results Major infrastructure projects rely on good working relationships, but when land is needed

  • Published On: February 7th, 2025

    Everyone is aware of the proposed Inheritance Tax changes for APR and BPR as set out in the October budget.  As we have previously highlighted, the statistics and analysis

  • Published On: February 7th, 2025

    This January the Rural Payments Agency (RPA) has re-launched a version of Higher-Tier Environmental Agreements for Farmers and Land Managers.   Initially by invitation only, the RPA’s new scheme is

  • Published On: February 7th, 2025

    Changes to the ‘standard method’ that the government use to estimate housing needs has led to significant increase in the number of homes that will need to be delivered

  • Published On: January 12th, 2025

    Across as wide range of infrastructure projects we are seeing an increasing number of compensation claims reaching the point of dispute and, with projects utilising compulsory acquisition powers set