Major Infrastructure and Compulsory Purchase
One of the intentions of the Planning Act 2008 was to make the permitting of major infrastructure projects more straightforward by combing planning consent and the Compulsory Purchase Order (CPO) into the Development Consent Order (DCO). It is debatable whether or not it has had the desired effect, rather than merely front loading the process to the statutory pre application stages which lie outside of the determination period set for PINS.
The governments own illustration above sets out the timelines involved in the DCO process, but it doesn’t show that the pre-application process is often between 3 and 5 years.
Either way, on approval the developer will have gained powers to obtain the specific land and rights that are required to carry out the development over land in which they have no existing legal interest. These developers are not only the large energy companies, authorities and agencies operating in the public good as one might expect, but include numerous private enterprises operating on a purely commercial basis.
We are starting to see more projects coming through the process from those that are high profile, such as HS2, to more local developments such as Wrexham Energy Centre and SPEN’s new 132kV line.
The developer is strongly encouraged by PINS to seek voluntary agreement to acquire land rights early in the DCO process, ideally before the application stage, but for affected landowners the threat of compulsory powers can often confuse their negotiating capacity.
Recent changes to the compulsory purchase rules have been brought in by Part 7 of the Housing and Planning Act 2016 and the government is consulting on further reforms, all of which makes the process more complicated than ever before.
Any landowners who are approached as being affected by a major infrastructure project should take expert advice before considering their next steps. There is often no need to be pushed into a hasty decision given the timeframes over which these projects gestate.
Related posts
The RPA have commenced the registration of users for the Basic Payment Scheme (BPS) via the new online facility. Many had been led to believe that a general notification
Having received planning permission for a second wind turbine in August the Ellis family have taken just three months to install and commission the machine. Completion of turbine one
Just over 12 months from Torridge District Councils decision to refuse a planning application for a single turbine on farmland Southwest of Bideford, North Devon, the Planning Inspectorate have allowed
With the next round of reforms to the Common Agricultural Policy (CAP) due to take effect at the start of 2015, the Secretary of State for Environment Food and
Wilson Fearnall have successfully overseen the planning and installation of another farm scale wind turbine at Mr & Mrs Ellis's Ty Isa Farm, just outside Cerrigydrudion near Corwen in
Today provisions that will allow agricultural buildings to be converted into residential dwellings under the General Permitted Development Order (permitted developments do not need full planning approval) came into